Vancouver International Airport (YVR) is Canada’s second busiest airport and North America’s second largest international passenger gateway on the West Coast with over 16 million passengers each year. YVR is located in Richmond, a suburb of Vancouver, at the mouth of the Fraser River, where the highest land point elevation is 1.8 meter (six feet) above sea level.
To meet its accelerating growth (21 million passengers by 2010), YVR has embarked upon a $200-million expansion of the International Terminal that includes 29,958 square meters (32,000 square feet) of new airport space, waiting areas, duty-free shops, services, and dining areas. The project also includes a baggage tunnel to be built underground, connecting the new terminal with the existing terminal. The underground tunnel created a significant challenge for the contractor due to the high water table.
Originally, specifications for the underground tunnel required that the tunnel be wrapped in a roofing membrane. The contractor, however, was concerned that the membrane might leak or be damaged while crews built the slab and walls. The original specifications also necessitated that the concrete cure for 28 days before the membrane could be applied. This curing period would mean an increase in the tunnel’s construction time of more than two months, delaying both the back filling of the area and the structural steel installation on the top of the tunnel.
The contractor, PCL, recommended Kryton’s Krystol concrete waterproofing system to waterproof the tunnel and to ensure that the ambitious schedule would be maintained. The world’s only permanent, in-depth, surface-applied waterproofing system, the Krystol concrete waterproofing system is a cementitious, chemically reactive treatment that turns existing concrete into a permanent and powerful waterproof barrier.
When added to the mix, Krystol’s crystalline chemicals grow millions of needle-like crystals throughout the concrete matrix, becoming a permanent part of the structure. Permanently blocking the movement of water in all directions. These crystals remain dormant until another crack forms, at which time they will react with incoming water to self-seal the crack and maintain a watertight seal.
The Krystol concrete waterproofing system for the YVR project includes:
Key factors in the YVR team’s decision to use the Krystol concrete waterproofing system:
The Krystol concrete waterproofing system saved one month in construction time and reduced material/application costs by more than 50 per cent over the originally specified membrane system.
Tunnel specifications: 4.5 m wide x 2.5 m tall x 35 m long (15 x 8.2 x1 15 feet)
Slab thickness: Floor 30 0mm, Walls 350 mm, Roof 355 mm (11.8 x 13.8 x 14 inches)
Total amount of KIM-treated concrete for the project: 340 cubic meters (445 cubic yards)
Krystol Internal Membrane (KIM) is a hydrophilic crystalline admixture used to create permanently waterproof concrete.
Krystol Waterstop Grout is a crystalline grout used to create an internal or external waterstop at construction joints, pipe penetrations, tie-holes and control joints.
Krystol Waterstop Treatment is a cementitious crystalline slurry that is applied to horizontal and vertical construction joints to provide additional waterproofing protection, and protect rebar from corrosion.
Krytonite Swelling Waterstop is a synthetic rubber waterstop that uses swelling pressure to seal concrete construction joints and stop water.
Kryton’s Crack Inducing Waterstop is specially engineered to produce a waterproof crack control joint.
The Krystol Waterstop System is used to permanently waterproof concrete construction joints, pipe penetrations, tie holes and control joints. The Krystol Waterstop System works where other waterstops routinely fail. Kryton is the only integral waterproofing company that offers fully integrated concrete waterproofing solutions. [more_toggle title="How…